• Blog: Weekly Update
  • Slide Show
  • Groundbreaking 2017
  • Project Overview
  • Project Contacts
  • Building Committee
  • Current Meetings
  • Facilities Plan 2017
  • Facilities Plan 2016
  • Facilities Plan 2015
  • Community Survey 2014
  • Capital Campaign 2013 (link)
  • Facilities Plan 2012
  • Needs Update 2010
  • Capital Campaign 2007
  • Facilities Plan 2007
  • Long Range Plan 2006
  • Needs Assessment 2002
  • Return to Library Homepage
Walter E. Olson Memorial Library Renovation and Expansion Project
 

Week Ending: 11/03/2017

11/6/2017

0 Comments

 
Work In Progress This Week and Completed to Date:
  • HVAC finish work
  •  Electrical finish work
  •  Fire protection finish work
  •  Plumbing finish work
  •  Epoxy floor install in basement
  •  Feature wall and wood window and door frames
  •  Final grade and seed
  •  Fence installed

Two Week Look Ahead:
  • FRP installation
  •  Data and phone finish work
  •  Fireplace masonry
  •  Ceiling field tile
  •  Vinyl wall covering installation
  •  Nana wall
  •  Gutters and downspouts
  •  Toilet partition installation
  •  Bathroom accessories and fire extinguisher install
  •  Doors and hardware
  •  Automatic door operators
  •  Carpet and vinyl base
  •  Hang decorative light fixtures
  •  Owner progress meeting November 9
Picture
Information desk
Picture
Study room (one of two)
Picture
Adult collection area looking toward the Information desk
Picture
0 Comments

Week Ending: 10/20/2017

10/23/2017

0 Comments

 
Work In Progress This Week and Completed to Date:
  • Siding work continued
  • Painting continued
  • Form and pour concrete for main and North walks
  • Asphalt and stripe parking lot
  • Ceiling grid and perimeter tile installed
  • HVAC finish work
  • Electrical finish work
  • Ceramic tile installation
  • Feature wall and wood window and door frames
  • Cabinet installation

Two Week Look Ahead:
  • Siding work
  • Vinyl wall covering installation
  • Ceiling grid and perimeter tile work to continue
  • Ceiling field tile
  • Nana wall
  • Fireplace masonry
  • Cabinet installation continues
  • Plumbing finish work
  • Fire protection finish work
  • Data phone finish work
  • Gutters and downspouts
  • Toilet partition installation
  • Bathroom accessories and fire extinguisher install
  • Doors and hardware
  • Carpet and vinyl base
  • Epoxy floor in basement
  • Owner progress meeting October 26
0 Comments

Week Ending: 10/06/2017

10/5/2017

0 Comments

 
Work In Progress This Week and Completed to Date:
· Masonry veneer work
· Soffit and fascia work complete
· Siding work continued
· Painting continued
· Existing tile removed
· Mechanical rough-ins above ceilings
· Prime and paint walls and ceilings
· Aluminum wall panels below windows
​
Two Week Look Ahead:
· Siding work
· Vinyl wall covering installation
· Aluminum wall panels below windows
· Ceiling grid and perimeter tile
· Fireplace masonry
· Ceramic tile installation
· Cabinet installation
· Plumbing finish work
· Owner progress meeting October 12
Picture
Picture
0 Comments

Week Ending: 09/22/2017

9/22/2017

0 Comments

 
Work In Progress This Week and Completed to Date:
  • Masonry veneer work
  • Soffit and fascia work
  • Siding work
  • Painting began

Two Week Look Ahead:
  • Siding, soffit and fascia work
  • Prime and paint door frames and walls
  • Aluminum wall panels below windows
  • Owner progress meeting September 28
Picture
0 Comments

Week Ending: 09/15/2017

9/20/2017

0 Comments

 
Work In Progress This Week and Completed to Date:
  • Tape and finish gypsum board
  • Masonry veneer work
  • Soffit and fascia work
  • Window in Director’s Office was installed
  • Owner progress meeting on September 14

Two Week Look Ahead:
  • Tape and finish gypsum board
  • Siding, soffit and fascia work
  • Prime and paint door frames and walls
  • Aluminum wall panels below windows
  • Owner progress meeting September 28
Picture
Picture
Picture
Picture
0 Comments

​Week Ending: 08/25/2017

8/29/2017

0 Comments

 
Work In Progress This Week and Completed to Date:
  • Framing complete
  • Insulation installation
  • Gypsum board installation

Two Week Look Ahead:
  • Gypsum board installation and sound insulation
  • Fireplace and venting install
  • Tape and finish gypsum board
  • Masonry
  • Aluminum entrances “Interior”
  • Aluminum wall panels below windows
  • Soffits, fascia, and siding
  • Owner progress meeting August 31
Picture
HVAC access (equipment located above restrooms
Picture
Children's space; east wall
Picture
looking into Technology space and Community Room
Picture
Children's space ; north wall
0 Comments

​Week Ending: 08/18/2017

8/22/2017

0 Comments

 
Work In Progress This Week and Completed to Date:
  • Phone and data wire rough-in complete
  • Frame interior walls and soffits
  • City walks and curbs were poured
  • Aluminum entrances began to be installed
  • Insulation installation
  • Owner progress meeting August 17

​Two Week Look Ahead:
  • Gypsum board installation and sound insulation
  • Fireplace and venting install
  • Tape and finish gypsum board
  • Masonry
  • Aluminum entrances “Interior”
  • Aluminum wall panels below windows
  • Soffits, fascia, and siding
  • Owner progress meeting August 31
Picture
Picture
0 Comments

Week Ending: 08/11/2017

8/16/2017

0 Comments

 
Work In Progress This Week and Completed to Date:
  • Mechanical rough-ins complete
  • Phone and data wire rough-in
  • Frame interior walls and soffits
  • Bryan is working on log design and samples
  • City walks and curbs were poured
  • Final electrical walk thru 8/10

Two Week Look Ahead:
  • Insulation
  • Gypsum board installation and sound insulation
  • Fireplace and venting install
  • Tape and finish gypsum board
  • Masonry
  • Aluminum Entrances
  • Siding, soffits and fascia
  • Owner progress meeting August 17
0 Comments

Week Ending: 07/28/2017

7/28/2017

0 Comments

 
Work In Progress This Week and Completed to Date:
  • Mechanical rough-ins continue
  • Frame interior walls and soffits
  • Basement was painted
  • Site walk thru to review electrical and data communication
  • Bryan is working on log design and samples
Two Week Look Ahead:
  • Plumbing, HVAC, and electrical rough-ins continue
  • Wood backing and blocking
  • Fireplace and venting install
  • Insulation
  • Gypsum board installation and sound insulation
  • Tape and finish gypsum board
  • Parking lot, cut to grade and stone
  • Masonry
  • Phone and data wire rough-in
  • Aluminum Entrances
  • Siding, soffits and fascia
  • Owner progress meeting August 3
0 Comments

Week Ending: 07/21/2017

7/26/2017

0 Comments

 
Work In Progress This Week and Completed to Date:
  • Mechanical rough-ins continue
  • Frame interior walls and soffits
  • Frame feature wall
  • Masonry veneer installation continues
  • Bryan is working on log design and samples
  • Owner progress meeting July 20
Two Week Look Ahead:
  • Plumbing, HVAC, and electrical rough-ins continue
  • Wood backing and blocking
  • Fireplace and venting install
  • Insulation
  • Gypsum board installation and sound insulation
  • Tape and finish gypsum board
  • Parking lot, cut to grade and stone
  • Masonry
  • Phone and data wire rough-in
  • Aluminum Entrances
  • Siding, soffits and fascia
  • Owner progress meeting August 3
0 Comments
<<Previous
    The Walter E. Olson Memorial Library remains open at 150 E. Hospital Road throughout the Expansion and Renovation Project at 203 N. Main Street. Visit this blog for updates on  construction status.

    Questions can be directed to nan@olsonlibrary.org

    Archives

    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017

    Categories

    All

    RSS Feed

Powered by Create your own unique website with customizable templates.