Work In Progress This Week and Completed to Date:
Two Week Look Ahead:
- Framing complete
- Insulation installation
- Gypsum board installation
Two Week Look Ahead:
- Gypsum board installation and sound insulation
- Fireplace and venting install
- Tape and finish gypsum board
- Masonry
- Aluminum entrances “Interior”
- Aluminum wall panels below windows
- Soffits, fascia, and siding
- Owner progress meeting August 31