Work Completed to date:
Two Week Look Ahead:
- Laid out interior walls and concrete trenching
- Erosion control
- Tree removal and capped dry well
- Excavation started for foundations
- Began framing interior walls
- Ground breaking ceremony
Two Week Look Ahead:
- Cut and remove concrete from trenches
- Cut and remove masonry from north wall
- Import and compact fill at north side of building
- Excavate for addition
- Pour concrete footings and foundations
- Backfill
- Underground plumbing and electrical work
- Owner progress meeting April 13 at 1:00 pm