Work Completed to date:
Two Week Look Ahead:
- Demolition of interior
- Siding demolition
- Started to layout interior walls
- Staked foundation
- Remaining light fixtures were taken down
Two Week Look Ahead:
- Excavation to start
- Ground breaking ceremony on March 30, Noon
- Progress meetings
- Continue to layout interior walls
- Begin framing interior walls
- HVAC trade partner complete demolition