Work In Progress This Week and Completed to Date:
- Siding work continued
- Painting continued
- Form and pour concrete for main and North walks
- Asphalt and stripe parking lot
- Ceiling grid and perimeter tile installed
- HVAC finish work
- Electrical finish work
- Ceramic tile installation
- Feature wall and wood window and door frames
- Cabinet installation
- Siding work
- Vinyl wall covering installation
- Ceiling grid and perimeter tile work to continue
- Ceiling field tile
- Nana wall
- Fireplace masonry
- Cabinet installation continues
- Plumbing finish work
- Fire protection finish work
- Data phone finish work
- Gutters and downspouts
- Toilet partition installation
- Bathroom accessories and fire extinguisher install
- Doors and hardware
- Carpet and vinyl base
- Epoxy floor in basement
- Owner progress meeting October 26