• Blog: Weekly Update
  • Slide Show
  • Groundbreaking 2017
  • Project Overview
  • Project Contacts
  • Building Committee
  • Current Meetings
  • Facilities Plan 2017
  • Facilities Plan 2016
  • Facilities Plan 2015
  • Community Survey 2014
  • Capital Campaign 2013 (link)
  • Facilities Plan 2012
  • Needs Update 2010
  • Capital Campaign 2007
  • Facilities Plan 2007
  • Long Range Plan 2006
  • Needs Assessment 2002
  • Return to Library Homepage
Walter E. Olson Memorial Library Renovation and Expansion Project
 

Week Ending: 05/19/2017

5/19/2017

0 Comments

 
Work In Progress This Week and Completed to Date:
  • Framing at existing/southwest corner
  • Roofing tear-off and dry-in
  • Utility trench

​Two Week Look Ahead:
  • Install sill flashings, wall foam, and air barrier
  • HVAC roof and wall penetrations
  • Plumbing, HVAC, and electrical rough-ins
  • Electrical rough-in walk through
  • Framing at addition (Steel columns, wood beams, and trusses)
  • Pour concrete floor
  • Exterior window install
  • Wall layout at addition
  • Frame interior walls, soffit, and mechanical mezz
  • Parking lot, cut to grade and stone
  • Owner progress meeting May 25 at 1:00 pm
0 Comments

Week Ending: 05/12/2017

5/12/2017

0 Comments

 
​Work In Progress This Week and Completed to Date:
  • Framing at existing structure
  •  Framing at addition
  •  Roof trusses for SW corner were set and removed temporary walls
  •  Started underground plumbing at addition

Two Week Look Ahead:
  •  Framing at addition (Steel columns, wood beams, and trusses)
  •  Install sill flashings, wall foam and air barrier
  •  Utility trench
  •  Parking lot, cut to grade and stone
  •  Underground mechanicals at addition
  •  Roofing tear-off and dry-in
  •  Owner progress meeting May 25 at 1:00 pm
0 Comments

Week Ending: 04/28/2017

5/2/2017

2 Comments

 
Work In Progress This Week and Completed to Date:
  • Underground mechanicals at existing structure
  • Framing at existing structure
  • Poured concrete in trenches at existing structure
  • Framing at addition
  • Owner progress meeting April 27 at 1:00 pm
 
 Two Week Look Ahead:
  • Framing at addition (Bearing walls, steel and wood beams)
  • Set roof trusses and bracing
  • Install sill flashings, wall foam and air barrier
  • Parking lot, cut to grade and stone
  • Underground mechanicals at addition
  • Owner progress meeting May 11 at 1:00 pm
Picture
Picture
Picture
Picture
2 Comments
    The Walter E. Olson Memorial Library remains open at 150 E. Hospital Road throughout the Expansion and Renovation Project at 203 N. Main Street. Visit this blog for updates on  construction status.

    Questions can be directed to nan@olsonlibrary.org

    Archives

    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017

    Categories

    All

    RSS Feed

Powered by Create your own unique website with customizable templates.