Work In Progress This Week and Completed to Date:
Two Week Look Ahead:
- Framing at existing structure
- Framing at addition
- Roof trusses for SW corner were set and removed temporary walls
- Started underground plumbing at addition
Two Week Look Ahead:
- Framing at addition (Steel columns, wood beams, and trusses)
- Install sill flashings, wall foam and air barrier
- Utility trench
- Parking lot, cut to grade and stone
- Underground mechanicals at addition
- Roofing tear-off and dry-in
- Owner progress meeting May 25 at 1:00 pm