Work In Progress This Week and Completed to Date:
Two Week Look Ahead:
- Underground mechanicals at existing structure
- Framing at existing structure
- Poured concrete in trenches at existing structure
- Framing at addition
- Owner progress meeting April 27 at 1:00 pm
Two Week Look Ahead:
- Framing at addition (Bearing walls, steel and wood beams)
- Set roof trusses and bracing
- Install sill flashings, wall foam and air barrier
- Parking lot, cut to grade and stone
- Underground mechanicals at addition
- Owner progress meeting May 11 at 1:00 pm