Work In Progress This Week and Completed to Date:
Two Week Look Ahead:
- Mechanical rough-ins continue
- Framing at addition (Steel columns, wood beams, and trusses)
- Foundations for stoops were poured
Two Week Look Ahead:
- HVAC roof and wall penetrations
- Plumbing, HVAC, and electrical rough-ins continue
- Pour concrete floor
- Set door frames
- Frame interior walls, soffit
- Install sill flashings, wall foam, and air barrier
- Exterior window install at addition
- Wood backing and blocking
- Fireplace and venting install
- Insulation
- Parking lot, cut to grade and stone
- Masonry veneer
- Owner progress meeting June 22