Work In Progress This Week and Completed to Date:
Two Week Look Ahead:
- Frame interior walls, soffit
- Install sill flashings, wall foam, and air barrier
- Exterior window install for existing building
- Mechanical rough-ins continue
- Set door frames
- Steel and trusses for the addition arrived on site
- Electrical rough-in walk through held on June 8
- Owner progress meeting on June 8
Two Week Look Ahead:
- HVAC roof and wall penetrations
- Plumbing, HVAC, and electrical rough-ins continue
- Framing at addition (Steel columns, wood beams, and trusses)
- Pour concrete floor
- Exterior window install
- Parking lot, cut to grade and stone
- Set door frames to continue
- Wood backing and blocking
- Fireplace and venting install
- Insulation
- Masonry veneer
- Owner progress meeting June 22