Work In Progress This Week and Completed to Date:
- Frame interior walls, soffit
- Install sill flashings, wall foam, and air barrier
- Partial window install
- Remove existing gas meter and line
- HVAC roof and wall penetrations
- Electrical rough-in walk through on June 8
- Plumbing, HVAC, and electrical rough-ins
- Framing at addition (Steel columns, wood beams, and trusses)
- Pour concrete floor
- Exterior window install
- Parking lot, cut to grade and stone
- Set door frames
- Wood backing and blocking
- Fireplace and venting install
- Insulation
- Masonry veneer
- Owner progress meeting June 8