Work In Progress This Week and Completed to Date:
- Mechanical rough-ins complete
- Phone and data wire rough-in
- Frame interior walls and soffits
- Bryan is working on log design and samples
- City walks and curbs were poured
- Final electrical walk thru 8/10
- Insulation
- Gypsum board installation and sound insulation
- Fireplace and venting install
- Tape and finish gypsum board
- Masonry
- Aluminum Entrances
- Siding, soffits and fascia
- Owner progress meeting August 17