Work In Progress This Week and Completed to Date:
Two Week Look Ahead:
- Tape and finish gypsum board
- Masonry veneer work
- Soffit and fascia work
- Window in Director’s Office was installed
- Owner progress meeting on September 14
Two Week Look Ahead:
- Tape and finish gypsum board
- Siding, soffit and fascia work
- Prime and paint door frames and walls
- Aluminum wall panels below windows
- Owner progress meeting September 28