Walter E. Olson Memorial Library Renovation and Expansion Project
 

​Week Ending: 07/14/2017

7/18/2017

0 Comments

 
Work In Progress This Week and Completed to Date:
  • Mechanical rough-ins continue
  • Frame interior walls and soffits
  • Masonry veneer installation
  • Electrical walk thru at addition on 7/13/17

​Two Week Look Ahead:
  • Plumbing, HVAC, and electrical rough-ins continue
  • Wood backing and blocking
  • Fireplace and venting install
  • Insulation
  • Gypsum board installation and sound insulation
  • Tape and finish gypsum board
  • Parking lot, cut to grade and stone
  • Masonry
  • Phone and data wire rough-in
  • Aluminum Entrances
  • Siding, soffits and fascia
  • Owner progress meeting July 20
0 Comments

Your comment will be posted after it is approved.


Leave a Reply.

    The Walter E. Olson Memorial Library remains open at 150 E. Hospital Road throughout the Expansion and Renovation Project at 203 N. Main Street. Visit this blog for updates on  construction status.

    Questions can be directed to nan@olsonlibrary.org

    Archives

    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017

    Categories

    All

    RSS Feed

Powered by Create your own unique website with customizable templates.