Work In Progress This Week and Completed to Date:
Two Week Look Ahead:
- Mechanical rough-ins continue
- Framing at addition
- Install sill flashings, wall foam, and air barrier
- Exterior window install at addition
- Concrete floor at addition
- Roof shingles
Two Week Look Ahead:
- Plumbing, HVAC, and electrical rough-ins continue
- Frame interior walls, soffit
- Wood backing and blocking
- Fireplace and venting install
- Insulation
- Parking lot, cut to grade and stone
- Masonry veneer
- Electrical walk thru at addition (Thursday 7/13/17, 10:30)
- Phone and data wire rough-in
- Owner progress meeting July 20