Work In Progress This Week and Completed to Date:
- Cut and remove concrete from trenches
- Import and compact fill at north side of building
- Excavate for addition
- Pour concrete footings and foundations
- Framing at existing structure
- Underground mechanicals at existing structure
- Pour concrete in trenches at existing structure
- Pour concrete footings and foundations
- Backfill
- Cut and remove masonry from north wall
- Framing at addition
- Owner progress meeting April 13 at 1:00 pm