Work In Progress This Week and Completed to Date:
Two Week Look Ahead:
- Underground mechanicals at existing structure
- Framing at existing structure
- Pour concrete footings and foundations
- Owner progress meeting was held April 13
Two Week Look Ahead:
- Concrete footings and foundations cure time
- Pour concrete in trenches at existing structure
- Backfill
- Cut and remove masonry from north wall
- Framing at addition (Bearing walls, steel and wood beams)
- Set roof trusses and bracing
- Storm water basins and piping
- Parking lot, cut to grade and stone
- Owner progress meeting April 27 at 1:00 pm